Barton Highway Roundabout Bridges
Client
Huon Contractors
Location
Canberra, ACT
Scope
☛ Construct a new cyclist bridge and upgrade the existing bridge.
☛ Build retaining walls and traffic barriers.
☛ Provide labor, plant, and temporary formwork materials for abutments, headstocks, bridge deck, approach slabs, retaining walls, and traffic barriers.
☛ Coordinate landing of Super T precast deck units and installation of bridge bearings.
Key Successes and Achievements
☛ All concrete works, including headstock blade walls, were completed free from non-conformance reports (NCRs) and met the specified tolerances and finish types.
☛ Achieved all construction milestones within the specified dates.
☛ Completed the project with zero lost time injuries.
☛ Minimised impact on the public and environment through in-depth planning, construction techniques, and risk assessments, despite the challenges of working adjacent to live traffic and over a watercourse.
Client
Huon Contractors
Location
Canberra, ACT
Contract Value
$690,000
Project Duration
8 months
Scope
☛ Build retaining walls and traffic barriers.
☛ Provide labor, plant, and temporary formwork materials for abutments, headstocks, bridge deck, approach slabs, retaining walls, and traffic barriers.
☛ Coordinate landing of Super T precast deck units and installation of bridge bearings.
Key Successes and Achievements
☛ All concrete works, including headstock blade walls, were completed free from non-conformance reports (NCRs) and met the specified tolerances and finish types.
☛ Achieved all construction milestones within the specified dates.
☛ Completed the project with zero lost time injuries.
☛ Minimised impact on the public and environment through in-depth planning, construction techniques, and risk assessments, despite the challenges of working adjacent to live traffic and over a watercourse.