Berrybank Wind Farm (Stage 2)

Client

Bielby

Location

Berrybank, VIC

Scope

☛ Constructed 26 monolithic foundation footings (19.2m diameter, 2.6m height).
☛ Installed 2,503m of electrical conduits (150mm diameter).
☛ Blinded 9,620m² of ground base.
☛ Poured 3,978m³ of concrete.
☛ Installed 5,408 M36 bolts.
☛ Placed 1,552 tonnes of reinforcing steel.
☛ Completed up to three foundations per week.
☛ Utilized specialized formwork systems for monolithic pours.

Key Successes and Achievements

☛ On-Time and On-Budget: Completed within the 6-month schedule and budget.
☛ Safety: Zero lost time injuries or environmental incidents.
☛ Quality: All works met client specifications and high-quality standards.
☛ Client Relationship: Fostered strong partnership with Bielby.
☛ Sector Leadership: Reinforced Nathan Contractors' role in the energy sector for FRP works.

Client

Bielby

Location

Berrybank, VIC

Contract Value

$2.6 million

Project Duration

6 months

Scope

☛ Installed 2,503m of electrical conduits (150mm diameter).
☛ Blinded 9,620m² of ground base.
☛ Poured 3,978m³ of concrete.
☛ Installed 5,408 M36 bolts.
☛ Placed 1,552 tonnes of reinforcing steel.
☛ Completed up to three foundations per week.
☛ Utilized specialized formwork systems for monolithic pours.

Key Successes and Achievements

☛ On-Time and On-Budget: Completed within the 6-month schedule and budget.
☛ Safety: Zero lost time injuries or environmental incidents.
☛ Quality: All works met client specifications and high-quality standards.
☛ Client Relationship: Fostered strong partnership with Bielby.
☛ Sector Leadership: Reinforced Nathan Contractors' role in the energy sector for FRP works.