Collector Wind Farm

Client

Civilex

Location

Breadalbane, NSW

Scope

Constructed 54 monolithic foundation footings for Vestas-engineered wind turbines.
☛ Installed 6 conduits per foundation.
☛ Placed 55m³ of blinding concrete for each foundation.
☛ Installed anchor cages and 232 M36 anchor bolts within the excavation.
☛ Placed 40 tonnes of steel reinforcement and 395m³ of structural concrete per foundation.
☛ Completed 3-4 foundations per week.
☛ Total installation of 2,160 tonnes of steel reinforcement and 24,300m³ of concrete.

Key Successes and Achievements

☛ On-Time and On-Budget: Completed within the 7-month schedule and budget, despite two weeks of stand-down time.
☛ Safety: Zero lost time injuries or environmental incidents.
☛ Quality: All works exceeded client specifications and strict tolerances.
☛ Client Relationship: Fostered a strong partnership with Civilex.
☛ Sector Competency: Reinforced Nathan Contractors' expertise in the energy sector for FRP works.

Client

Civilex

Location

Breadalbane, NSW

Contract Value

$5.0 million

Project Duration

7 months

Scope

Constructed 54 monolithic foundation footings for Vestas-engineered wind turbines.
☛ Placed 55m³ of blinding concrete for each foundation.
☛ Installed anchor cages and 232 M36 anchor bolts within the excavation.
☛ Placed 40 tonnes of steel reinforcement and 395m³ of structural concrete per foundation.
☛ Completed 3-4 foundations per week.
☛ Total installation of 2,160 tonnes of steel reinforcement and 24,300m³ of concrete.

Key Successes and Achievements

☛ On-Time and On-Budget: Completed within the 7-month schedule and budget, despite two weeks of stand-down time.
☛ Safety: Zero lost time injuries or environmental incidents.
☛ Quality: All works exceeded client specifications and strict tolerances.
☛ Client Relationship: Fostered a strong partnership with Civilex.
☛ Sector Competency: Reinforced Nathan Contractors' expertise in the energy sector for FRP works.