Collector Wind Farm
Client
Civilex
Location
Breadalbane, NSW
Scope
Constructed 54 monolithic foundation footings for Vestas-engineered wind turbines.
☛ Installed 6 conduits per foundation.
☛ Placed 55m³ of blinding concrete for each foundation.
☛ Installed anchor cages and 232 M36 anchor bolts within the excavation.
☛ Placed 40 tonnes of steel reinforcement and 395m³ of structural concrete per foundation.
☛ Completed 3-4 foundations per week.
☛ Total installation of 2,160 tonnes of steel reinforcement and 24,300m³ of concrete.
Key Successes and Achievements
☛ On-Time and On-Budget: Completed within the 7-month schedule and budget, despite two weeks of stand-down time.
☛ Safety: Zero lost time injuries or environmental incidents.
☛ Quality: All works exceeded client specifications and strict tolerances.
☛ Client Relationship: Fostered a strong partnership with Civilex.
☛ Sector Competency: Reinforced Nathan Contractors' expertise in the energy sector for FRP works.
Client
Civilex
Location
Breadalbane, NSW
Contract Value
$5.0 million
Project Duration
7 months
Scope
Constructed 54 monolithic foundation footings for Vestas-engineered wind turbines.
☛ Placed 55m³ of blinding concrete for each foundation.
☛ Installed anchor cages and 232 M36 anchor bolts within the excavation.
☛ Placed 40 tonnes of steel reinforcement and 395m³ of structural concrete per foundation.
☛ Completed 3-4 foundations per week.
☛ Total installation of 2,160 tonnes of steel reinforcement and 24,300m³ of concrete.
Key Successes and Achievements
☛ On-Time and On-Budget: Completed within the 7-month schedule and budget, despite two weeks of stand-down time.
☛ Safety: Zero lost time injuries or environmental incidents.
☛ Quality: All works exceeded client specifications and strict tolerances.
☛ Client Relationship: Fostered a strong partnership with Civilex.
☛ Sector Competency: Reinforced Nathan Contractors' expertise in the energy sector for FRP works.



