Cotter Road Stage 2 Duplication and Shared Path Works
Client
Huon Contractors Pty Ltd
Location
Canberra, ACT
Scope
☛ Construction of two single-span Super Tee girder bridges.
☛ Erection of 752 meters of noise wall.
☛ Building 160 meters of retaining walls.
☛ Construction of new kerbs and traffic barriers on Bridge 4124.
☛ FRP works for abutments, headstocks, concrete decks, traffic barriers, noise walls, retaining walls, concrete barriers, and kerbs.
☛ Landing of Super Tee girders and FRP of cross girders.
Key Successes and Achievements
☛ By adapting to changes in the construction program and sequence of works, Nathan Contractors optimized resource allocation, including formwork systems, scaffold, and craneage. This strategic adjustment minimized disruptions and maintained project momentum.
☛ All works were completed in strict compliance with RMS NSW specifications, ensuring high-quality finishes and durability. The project has had no recalls for defects, reflecting Nathan Contractors' commitment to excellence.
☛ The project provided valuable insights and developed construction efficiencies that have been leveraged to secure and successfully execute subsequent bridge projects, demonstrating Nathan Contractors' strategic approach to continuous improvement and competitive advantage in the industry.
Client
Huon Contractors Pty Ltd
Location
Canberra, ACT
Contract Value
$1,684,000
Project Duration
12 months
Scope
☛ Erection of 752 meters of noise wall.
☛ Building 160 meters of retaining walls.
☛ Construction of new kerbs and traffic barriers on Bridge 4124.
☛ FRP works for abutments, headstocks, concrete decks, traffic barriers, noise walls, retaining walls, concrete barriers, and kerbs.
☛ Landing of Super Tee girders and FRP of cross girders.
Key Successes and Achievements
☛ By adapting to changes in the construction program and sequence of works, Nathan Contractors optimized resource allocation, including formwork systems, scaffold, and craneage. This strategic adjustment minimized disruptions and maintained project momentum.
☛ All works were completed in strict compliance with RMS NSW specifications, ensuring high-quality finishes and durability. The project has had no recalls for defects, reflecting Nathan Contractors' commitment to excellence.
☛ The project provided valuable insights and developed construction efficiencies that have been leveraged to secure and successfully execute subsequent bridge projects, demonstrating Nathan Contractors' strategic approach to continuous improvement and competitive advantage in the industry.