Dalby Dryer
Client
Walz Constructions
Location
Bio Refinery Plant, Dalby, QLD
Scope
☛ Supply and place 620m³ of concrete.
☛ Supply and tie 78 tonnes of reinforcement.
☛ Supply and erect 360m² of formwork to slabs, plinths, and beams.
☛ Install 65 piles to a maximum depth of 9m.
☛ Conduct earthworks, detailed excavation, drainage, install electrical conduits, and supply and place gravel pavements.
Key Successes and Achievements
☛ Completed within the three-month schedule and budget.
☛ Zero lost time injuries.
☛ Successfully positioned all holding down bolts within tolerance.
☛ Constructed piles using plastic liners and placed underlying styrene to required tolerances, complying with design specifications despite challenges with design level differences.
Client
Walz Constructions
Location
Bio Refinery Plant, Dalby, QLD
Contract Value
$1.31 million
Project Duration
3 months
Scope
☛ Supply and tie 78 tonnes of reinforcement.
☛ Supply and erect 360m² of formwork to slabs, plinths, and beams.
☛ Install 65 piles to a maximum depth of 9m.
☛ Conduct earthworks, detailed excavation, drainage, install electrical conduits, and supply and place gravel pavements.
Key Successes and Achievements
☛ Completed within the three-month schedule and budget.
☛ Zero lost time injuries.
☛ Successfully positioned all holding down bolts within tolerance.
☛ Constructed piles using plastic liners and placed underlying styrene to required tolerances, complying with design specifications despite challenges with design level differences.



