Paradise Dam Spillway Upgrade – Stage 2

Client

SunWater Limited

Location

Childers, QLD

Scope

☛ Construct 7 x 45m long infill steps and 2 x 45m tie-in steps.
☛ Modify and repair the Left Bank Training Wall and Left Bank Stairs.
☛ Perform hydro-demolition of 40m³ of concrete.
☛ Conduct concrete break back and surface preparation of 560m² of existing concrete.
☛ Install and chemically epoxy 1,769 anchor bars.
☛ Supply and install 60 tonnes of reinforcing steel.
☛ Install and chemically inject waterstop.
☛ Formwork and concrete placement for 320m³ of concrete.

Key Successes and Achievements

☛ Completed the project within the 4-month schedule and under budget.
☛ Zero lost time injuries or environmental incidents.
☛ All concrete placements met client specifications for temperature, dimensional tolerances, and finish.
☛ Successfully addressed challenges with tie-in pours through test pours, mix design changes, and advanced formwork techniques.

Client

SunWater Limited

Location

Childers, QLD

Contract Value

$2.24 million

Project Duration

4 months

Scope

☛ Modify and repair the Left Bank Training Wall and Left Bank Stairs.
☛ Perform hydro-demolition of 40m³ of concrete.
☛ Conduct concrete break back and surface preparation of 560m² of existing concrete.
☛ Install and chemically epoxy 1,769 anchor bars.
☛ Supply and install 60 tonnes of reinforcing steel.
☛ Install and chemically inject waterstop.
☛ Formwork and concrete placement for 320m³ of concrete.

Key Successes and Achievements

☛ Completed the project within the 4-month schedule and under budget.
☛ Zero lost time injuries or environmental incidents.
☛ All concrete placements met client specifications for temperature, dimensional tolerances, and finish.
☛ Successfully addressed challenges with tie-in pours through test pours, mix design changes, and advanced formwork techniques.