Paradise Dam Spillway Upgrade – Stage 2
Client
SunWater Limited
Location
Childers, QLD
Scope
☛ Construct 7 x 45m long infill steps and 2 x 45m tie-in steps.
☛ Modify and repair the Left Bank Training Wall and Left Bank Stairs.
☛ Perform hydro-demolition of 40m³ of concrete.
☛ Conduct concrete break back and surface preparation of 560m² of existing concrete.
☛ Install and chemically epoxy 1,769 anchor bars.
☛ Supply and install 60 tonnes of reinforcing steel.
☛ Install and chemically inject waterstop.
☛ Formwork and concrete placement for 320m³ of concrete.
Key Successes and Achievements
☛ Completed the project within the 4-month schedule and under budget.
☛ Zero lost time injuries or environmental incidents.
☛ All concrete placements met client specifications for temperature, dimensional tolerances, and finish.
☛ Successfully addressed challenges with tie-in pours through test pours, mix design changes, and advanced formwork techniques.
Client
SunWater Limited
Location
Childers, QLD
Contract Value
$2.24 million
Project Duration
4 months
Scope
☛ Modify and repair the Left Bank Training Wall and Left Bank Stairs.
☛ Perform hydro-demolition of 40m³ of concrete.
☛ Conduct concrete break back and surface preparation of 560m² of existing concrete.
☛ Install and chemically epoxy 1,769 anchor bars.
☛ Supply and install 60 tonnes of reinforcing steel.
☛ Install and chemically inject waterstop.
☛ Formwork and concrete placement for 320m³ of concrete.
Key Successes and Achievements
☛ Completed the project within the 4-month schedule and under budget.
☛ Zero lost time injuries or environmental incidents.
☛ All concrete placements met client specifications for temperature, dimensional tolerances, and finish.
☛ Successfully addressed challenges with tie-in pours through test pours, mix design changes, and advanced formwork techniques.



