Rocklands Copper Mine, QLD

Client

Cudeco Ltd

Location

Cloncurry, QLD

Scope

☛ Earthworks and detailed excavation.
☛ Concrete footings, foundations, and slabs for processing equipment.
☛ Construction of over 500 pedestal footings for pipe racks and conveyor systems.
☛ E-House and Tunnel slabs, including 20 independent concrete slabs for electrical switching rooms.
☛ Construction of over 300 pedestals for electrical cabling trays.
☛ Major slab for feed conveyor from stockpile to crusher.
☛ Construction of 5 bunkers for electrical transformers and numerous isolated pedestals for pipework.
☛ Placement of over 2,500m³ of concrete and 240 tonnes of steel reinforcement.
☛ Erection of 1,100m² of wall form, preparation of 12,000m² of subgrade, and more than 2,000m³ of detailed excavation.

Key Successes and Achievements

☛ Completed within the 12-month schedule.
☛ No major incidents, maintaining high safety and environmental standards.
☛ All concrete and cast-in elements met technical specifications and tolerances.
☛ Awarded additional scope due to ability to meet tight program requirements without sacrificing quality, safety, and environmental controls.

Client

Cudeco Ltd

Location

Cloncurry, QLD

Contract Value

$9.34 million

Project Duration

12 months

Scope

☛ Concrete footings, foundations, and slabs for processing equipment.
☛ Construction of over 500 pedestal footings for pipe racks and conveyor systems.
☛ E-House and Tunnel slabs, including 20 independent concrete slabs for electrical switching rooms.
☛ Construction of over 300 pedestals for electrical cabling trays.
☛ Major slab for feed conveyor from stockpile to crusher.
☛ Construction of 5 bunkers for electrical transformers and numerous isolated pedestals for pipework.
☛ Placement of over 2,500m³ of concrete and 240 tonnes of steel reinforcement.
☛ Erection of 1,100m² of wall form, preparation of 12,000m² of subgrade, and more than 2,000m³ of detailed excavation.

Key Successes and Achievements

☛ Completed within the 12-month schedule.
☛ No major incidents, maintaining high safety and environmental standards.
☛ All concrete and cast-in elements met technical specifications and tolerances.
☛ Awarded additional scope due to ability to meet tight program requirements without sacrificing quality, safety, and environmental controls.